CES served as the commissioning agent for the construction of this new, modern public safety complex. Construction of this facility will meet the long-term needs of the University’s public safety operation and will allow the police department to absorb additional security related technology.

This structure is located in close proximity to East Hall (Facilities Management) and the Energy Center, which will facilitate access to site utilities and provide easy access to the surrounding roadway systems. Integral to the operations of this department and personnel requirements is the construction of a state-of-the-art Communications Center and Critical Incident Response Room for 24-hour monitoring of campus activities.

Systems Commissioned Include:

  • Hot water heating system including boilers, pumps, valves, VFDs, etc
  • AC-1
  • Rooftop units
  • Computer room air conditioning units
  • VAV boxes
  • Radiation including fin tube and radiant panels
  • Exhaust fans
  • Unit heaters
  • Cabinet unit heaters
  • The building management system
  • Tab spot check
  • Domestic hot water heater, storage and re-circulation system and associated components
  • Water closets and sinks
  • Lighting and lighting control
  • Emergency generator and ATS
  • Fire alarm system
  • Technology